Preconstruction decides whether your project runs smoothly or becomes a story you tell at dinner parties. This checklist covers every item to settle before a crew starts work on your project. Work through it in order.

Do not start construction with items still open.

Read the full guide: What Does Preconstruction Mean?

Every Timber project begins with a preconstruction phase. We work in Ulster, Dutchess, Orange and Sullivan counties, so the examples below are local.

PHASE 1: Program and Goals

Before a designer draws a line, confirm what the project is trying to accomplish. Settle these items first.

  • Define the project type: new construction, renovation, addition, ADU, or combination
  • Write a room-by-room program: what each space needs to contain and how it needs to function
  • Separate must-haves from nice-to-haves
  • Know what gets cut first, because budget will shape the project
  • Establish the budget ceiling: the maximum amount the project can cost
  • Establish the budget floor: the minimum spend that accomplishes the core goals
  • Identify any non-negotiable design requirements (e.g., a specific kitchen configuration, a home office, a view orientation)
  • Confirm the project timeline: is there a hard completion date? A seasonal constraint? A financing milestone?
  • Identify who makes decisions: one person, or two people who need to agree

Learn about Program Development in Preconstruction

PHASE 2: Site Assessment

Site assessment confirms what the parcel allows: boundaries, flood zone, zoning, setbacks, bedrock, septic, well, and access. Check each item before design goes far.

  • Confirm the address and parcel boundaries. This matters most where two governments share a name. New Paltz has a Village and a Town. Newburgh and Poughkeepsie each have a City and a Town.
  • Obtain and review the current survey (if one exists)
  • Review the FEMA Flood Insurance Rate Map for the parcel. Is any portion in Zone AE or AO?
  • Research the zoning district and confirm the project type is permitted by right
  • Confirm setback requirements for the proposed work
  • Calculate current lot coverage and confirm the project fits within allowable coverage
  • Bedrock assessment: Near the Shawangunk Ridge or in mountain terrain, confirm bedrock depth before finalizing foundation type
  • Septic: Adding bedroom equivalents or new dwelling units? Before design, contact the county health department for a septic capacity assessment.
  • Well: On a private well, confirm well yield is adequate for expanded occupancy
  • Review site access: can construction equipment reach the site? Is the driveway adequate for concrete trucks and material delivery?

PHASE 3: Municipality and Permit Research

Permit research confirms who reviews your project and what they require. Do not assume the permit is straightforward.

  • Confirm the correct jurisdiction for permit filing: City or Town, Village or Town. Many Hudson Valley municipalities keep these separate.
  • Contact the building department. Confirm what documents a permit application requires.
  • Historic district check. Confirm whether the property is in:
  • Determine whether a variance is required (setback encroachment, height, lot coverage)
  • For new construction or additions, determine whether Planning Board site plan review is required
  • Research the typical permit review timeline for this municipality
  • Renovating an older building? Ask whether the municipality requires asbestos survey documentation before permit issuance.
  • For ADU projects, confirm the municipality's current ADU rules

Planning a project in Ulster, Dutchess, Orange or Sullivan County? Call (845) 500-3002 or schedule a camera-on Zoom call.

PHASE 4: Design and Engineering

Design and engineering turn the program into permit-ready drawings. Each item below should be complete before you price the work.

  • Confirm the design delivery model: design-build (one team), or separate architect and contractor. Compare them in Design-Build vs. GC
  • Schematic design complete: floor plans, elevations, and sections showing the full project scope
  • Design review: does the design achieve the program? Does it fit within the budget?
  • Structural engineering engaged for any project involving wall removal, new openings, additions, or new construction
  • For projects in historic districts: design reviewed against Secretary of Interior Standards before permit application
  • MEP design coordination: mechanical, electrical, and plumbing systems designed and coordinated with architecture
  • For kitchen projects: cabinet elevations complete with dimensions confirmed against as-built measurements
  • For bathroom projects: tile layout planned, wet area waterproofing system specified
  • Material specifications complete: flooring, tile, countertops, hardware, fixtures
  • Construction documents (permit-ready drawings) complete

PHASE 5: Budget and Contract

Budget and contract work fixes the price and the terms before work starts. Price the project from complete drawings, not a rough estimate.

  • Line-item cost estimate developed from complete drawings, not a rough estimate
  • Allowances established for items not yet fully specified (tile, fixtures, appliances)
  • Contingency established: 10% for well-understood scope, 15–20% for older homes and gut renovations
  • Budget reviewed against the program from Phase 1. Does the cost match what was planned?
  • Alternates identified: items that can be added or removed to adjust total cost
  • Contract reviewed: scope is documented, change order process is defined, payment schedule is established
  • Certificate of insurance confirmed: general liability and workers' compensation from contractor

PHASE 6: Pre-Construction Logistics

Logistics are the last items to close before the crew arrives. Check each one off.

  • Permit approved (or submitted and in review)
  • Long-lead materials ordered: windows, doors, specialty tile, custom cabinetry
  • Living arrangements confirmed for the duration of the project
  • Site access confirmed: contractor staging area, dumpster placement, delivery access
  • Neighbors notified where appropriate, especially in historic districts or on tight urban lots
  • Utilities located before any excavation begins. Contact UDig NY at 811 before you dig.
  • Hazardous material survey complete for older buildings if required

Learn about our Preconstruction Services · Read the Home Renovation Checklist · Start Your Project

FAQ

Is this checklist for custom homes, renovations, or both?

Both. The framework is the same, but Phases 2 and 3 apply differently. New construction needs more site and zoning work. A renovation needs more assessment of existing conditions.

How far in advance should preconstruction start?

Start preconstruction for a renovation 3–5 months before your desired construction start. For a custom home, start 6–12 months ahead. In municipalities with historic district review, add 2–3 months to the front end.

What's the most commonly incomplete item when people start construction too early?

Phase 3, permit research. The assumption that permits are straightforward delays more projects than any other single item. Watch for a missing septic approval or an unexpected historic district requirement. A variance needs Zoning Board of Appeals approval too. Found after design is complete, any one can delay a project start by 3–6 months.

Sources

Checked 24 Nov 2026. Rules change, so confirm with your own building department.